Method Statement for Probing and Grouting Treatment
CAVITY AND SLUMP-ZONE PROBING & GROUTING TREATMENT TABLE OF CONTENTS 1.0 WORK ORGANISATION 2.0 DESIGN CONSTRAINTS AND COORDINATION 3.0 CONTRACTING METHODS 4.0 PROCUREMENT METHODS 5.0 RESOURCE PROVISIONS 6.0 LOGISTICS PROVISIONS 7.0 MATERIAL MANAGEMENT SYSTEMS 8.0 CONSTRUCTION METHODS AND TECHNOLOGY 9.0 CONSTRUCTION PHASING AND WORKFLOW 10.0 TRAFFIC MANAGEMENT AND MONITORING 11.0 SAFETY PROGRAM 12.0 QUALITY ASSURANCE AND CONTROL PROGRAMS 13.0 INDUSTRIAL RELATIONS POLICIES 14.0 ENVIRONMENTAL MONITORING PROGRAMS 15.0 APPENDICES 1.0 INTRODUCTION This submission explains the method of construction to be adopted for the Cavity and Slump-zone Probing and treatment at the project site. 2.0 DESIGN CONSTRAINTS AND COORDINATION Not applicable. 3.0 CONTRACTING METHOD The conditions of Contract have been reviewed by PCSB and particularly those conditions in respect of Sub-PCSBs. The conditions are bespoke for this project and therefore be required to be reflected in any form of subcontract