Posts

Showing posts from 2020

Prime Coat (MC-1)

Image
Prime coat typically is application of low viscosity Bitumen over a granular base, preparing it for laying an asphalt mixture on it. A prime coat performs several important functions. Coats and bonds loose material particles on the surface of the base. Hardens or toughens the surface of the base. Waterproofs the surface of the base by plugging capillary or interconnected voids Provides adhesion or bond between the base and the asphalt mixture. Bitumen emulsions used for Prime Coat are Cationic Slow Setting Emulsion 1 and Cationic Slow Setting Emulsion 2 as per latest MoRTH specifications.

Factors to be taken care, prior to placement of Concrete!

Major factor should be considered when placing the concrete on-site delivered from the batching plant/Mixing plant, Many and varied below:- Ambient temperature (The Weather During the Casting Time) Specification for the Mix Design Sub-grade Condition Type of Installation (Lean, Structure, Column, Beam, etc.) Form Securement Type of reinforcement Sufficient personnel capable of placing the concrete. Pouring Rate Height of Free Fall of Concrete must not be more than 1.2 m. Avoid Cold Joints

Common Types of Problems in Concrete during Placement!

Image
Common Concrete Pouring Issues 1. AIR LOSS: During concrete pouring, air loss can cause problems. Several factors lead to this, such as long vertical drops, high initial slump, increase in pressure, or drop in exit. For every 1% decrease in air, strength decreases by 4-5%. You can fix this problem by adding a gate at the end of the pump line for restriction. It also helps to keep the boom in an upward or horizontal position as much as possible. If this can’t be done you can put multiple 90 degree elbows into the line to slow down concrete, minimizing the straight dropout. 2. BUG HOLES: Bug holes are evident by a small void on the outside of formed concrete surfaces. These come from poor application of form release agents to form-work or completely forgoing their use entirely. It can also come from stiff or sticky concrete mixtures. This can also be caused by poorly placed internal concrete vibrators. To solve the problem of bug holes, make sure release agents are applied

What is a Method Statement and How do I Write One?

Image
Method statements, sometimes called ‘a safe system of work’ are documents that detail the way in which tasks should be completed to adhere to safe working practices. But how do you write them?  What tasks do you need them for? And how do they help you win business? There's method to this madness! Method statements demonstrate that you’re doing things safely and legally, which can give you a  competitive edge when pitching for projects and they usually go hand in hand with Risk Assessments. Do I need a Method Statement? Method Statements are frequently requested as part of tender processes to gain an insight into your  organisation and the way you operate. It’s your opportunity to show how you’ll provide goods and  services in a safe and high-quality manner. Writing a Method Statement may seem like a daunting task, but this article will guide you through  the process and enable you to approach Method Statements with confidence. What's the benefit of ha

Things to Consider about Hot Weather Concreting

THINGS TO CONSIDER ABOUT HOT WEATHER CONCRETE When the temperature of freshly mixed concrete approaches approximately  32 ° C  adverse site conditions can impact the quality of concrete. Ambient temperatures above  40 ° ​ C  and the lack of a protected environment for concrete placement and finishing (like enclosed building) can contribute to difficulty in producing quality concrete. The precautions required to ensure a quality end product will vary depending on the actual conditions during concrete placement and the specific application for which the concrete will be used. In general, if the temperature at the time of concrete placement will exceed  32 ° C  a plan should be developed to negate the effects of high temperatures. The precautions may include some or all of the following: Moisten sub-grade, steel reinforcement, and form work prior to concrete placement. Erect temporary wind breaks to limit wind velocities and sunshades to reduce concrete surface temperatur

Method Statement for Probing and Grouting Treatment

CAVITY AND SLUMP-ZONE PROBING & GROUTING TREATMENT TABLE OF CONTENTS 1.0 WORK ORGANISATION 2.0 DESIGN CONSTRAINTS AND COORDINATION 3.0 CONTRACTING METHODS 4.0 PROCUREMENT METHODS 5.0 RESOURCE PROVISIONS 6.0 LOGISTICS PROVISIONS 7.0 MATERIAL MANAGEMENT SYSTEMS 8.0 CONSTRUCTION METHODS AND TECHNOLOGY 9.0 CONSTRUCTION PHASING AND WORKFLOW 10.0 TRAFFIC MANAGEMENT AND MONITORING 11.0 SAFETY PROGRAM 12.0 QUALITY ASSURANCE AND CONTROL PROGRAMS 13.0 INDUSTRIAL RELATIONS POLICIES 14.0 ENVIRONMENTAL MONITORING PROGRAMS 15.0 APPENDICES 1.0 INTRODUCTION This submission explains the method of construction to be adopted for the Cavity and Slump-zone Probing and treatment at the project site. 2.0 DESIGN CONSTRAINTS AND COORDINATION Not applicable. 3.0 CONTRACTING METHOD The conditions of Contract have been reviewed by PCSB and particularly those conditions in respect of Sub-PCSBs. The conditions are bespoke for this project and therefore be required to be reflected in any form of subcontract

Overview of Codes and Standards in Saudi Arabia

Image

Procedure for Material Inspection Request (MIR)

Once you obtained the Approval of Material (SAM) for the certain material. You are now ready to check the material arrived on site. Now! This might be your question “What if the material arrived is not yet approved, what will I do?” Here is what you will do and in case that the material is being reviewed by consultant and it’s eventually be approved later then you may still submit the material inspection with comment as “Awaiting approval.” Here are the steps to follow to checking the materials on your site at the first time. 1. Obtain Delivery Note: Always ask your storekeeper for the arrived material on site and collect the delivery note of that. Just make a routine every morning or every other day on this task, especially if the project has just started. It is expected that there will be volumes of materials that will be arriving. This should be your initiative as a quality assurance and quality control engineer, be proactive on this task. In case you are handling subcontractor, th

Inspection Testing Plan (ITP) VS Checklist

Image
DEFINITION OF ITP? An Inspection and Test Plan (ITP) lays out a schedule of inspections at critical control points or 'hold points' within a process, in order to verify that things are progressing as they should be. It can be defined as the program of inspection, testing of materials, and survey to be prepared and submitted by the contractor to the Consultant for approval before usage and application to the site. An "Inspection and Test Plan" (ITP) might also be called a "Quality Inspection Plan (QTP)". Inspection and Test Plans set out critical control points or ' hold points ' at various stages within a process. Each control point is a scheduled inspection or verification activity, where you will make sure that things are progressing as they should be. Inspection and Test Plans (ITP) are often used as a way to satisfy the requirements of the ISO 9001:2015 standard related to control of production and service provision. Did yo