Method Statement for Excavation and Back filling Works
1. Scope 1.1 This Method Statement describes a proper work procedure shall be carried out during the excavation stage as per specification and contract drawings. 2. References 2.1 General Specification – Excavation & Earthworks 3. Materials 3.1 Natural Soil 4. Tools & Equipment 4.1 Excavator 4.2 Pay Loader 4.4 JCB / Poclain 4.5 Six Wheel Truck 4.6 Bob-Cat 4.7 Shovel 4.8 Total Station 4.9 Meter Tape 5. Work Procedure 5.1 Site Preparation 5.1.1 Existing Services – [Company] construction team would conduct an investigation and acquire information about site services might have been placed/embedded below the ground. Services, wherever found shall be rerouted and protected to place will not affect site activities. 5.1.2 Setting out – [Company] surveyor would conduct the site survey to mark/stake-out the lines and levels of the objective excavation for foundations as per indicated in the approved drawing. 5.2 Excavation 5.2.1 The area to be...